Construction
24
Work
continues on the construction site. Steel framing is now
complete on the front side of the building. The crane has
been moved to the Main Street side to finish steel there.
Workers are finishing bolting and welding connections while
other trades now begin other systems in the building. Power
switch panel has been put into position while electrician
begins wiring the building. AV boxes can be seen in the
stage.